高铁隧道施工顺序
更新时间: 2021-03-04 10:25:31  

施工准备-超前地质预报-测量放线-开挖(开挖方法有:台阶开挖、双侧壁开挖、CD法开挖等)-装药爆破-通风排烟-初喷混凝土-初支-监控测量-开挖(根据开挖方式的不同而定)。每做一次开挖均要进行支护(根据施工方式的不同,支护方式分为:永久支护和临时支护),临时支护于完毕时需进行拆除。

关键词: 隧道 施工 顺序

高铁隧道施工顺序相关经验

天气预报

最新推荐

页面:/news/view-1311075/ | 耗时:0.7563 s | 内存:2.11 MB | 查询:4 | 缓存读取:3 写入:0 | 加载文件:25
select * from tbl_Articles WHERE ArticleID=1311075 LIMIT 0,1
select * from tbl_Articles_data WHERE ArticleID=1311075 LIMIT 0,1
select * from tbl_Articles_sphinx where id=1311075 LIMIT 0,1
SELECT ArticleID,Title FROM tbl_Articles WHERE ArticleID IN(3414182,797767,513747,3045069,2675239,1085431,3084116,4078432,3500098,1311075,3500448,382804,2403176,840405,1023146,3292773,2458377,513065,496231,1032907,1320021,2782137,1015244,480848,821594,399873,438764,857346,1783679,2687675) ORDER BY field (ArticleID,3414182,797767,513747,3045069,2675239,1085431,3084116,4078432,3500098,1311075,3500448,382804,2403176,840405,1023146,3292773,2458377,513065,496231,1032907,1320021,2782137,1015244,480848,821594,399873,438764,857346,1783679,2687675)